Bringing Hope and Life to the Community
CBO Updates
CBO update on utilization of the Funds Raised through three Harambees On: November 27, 2021; July 29, 2025; and June 8, 2024 respectively.
The CBO organized three fundraising events (Harambees), raising KES. 267,203, KES. 836,850, and KES. 809,286 respectively, for a total of KES. 1,913,339. The funds have been utilized on the CBO health facility project as follows;
- Purchased 1-acre land and provided land survey services to formalize the purchase.
- Engaged architects to develop designs for the CBO health facility.
- Purchased fencing materials and installed the fence at the health facility CBO site.
- Obtained approval for the health facility’s architectural designs from government authorities, including public health, physical planning, urban development, and the National Environmental Management Authority.
- Purchased building materials for the Doctor’s Quarters.
- Construction of the Doctor’s Quarters is 50% complete.